Power networks/Portugal

This page describes the electrical power network of Portugal (Q45), including the archipelagos of the Azores (Q25263) and Madeira (Q26253). It also provides guidance on how to map the network accurately in OSM.
The information presented here applies specifically to the mainland Portuguese transmission and distribution grid. While the power systems of the Azores and Madeira differ in certain structural and operational aspects, they follow the same fundamental principles. It should be noted that the two archipelagos operate independent power networks, managed by separate entities, and are not electrically interconnected with continental Portugal.
Organization
The electricity system in continental Portugal is managed in a single-operator/monopoly regime, as a result of forcible nationalizations and mergers in the period of 1974-1976. Until 1994, the only power network operator, also operating the majority of power production capacity, was EDP - Eletricidade de Portugal, in a vertically integrated monopoly. The most relevant change since was that the ownership and operation of the transmission grid was first placed under REN - Redes Energéticas Nacionais with complete ownership of EDP, with REN leaving the sphere of influence of EDP after being privatized in 2000.
Grid operators
In Continental Portugal, the larger operators are:
- REN (Q1862842), very-high voltage (150-400kV) transmission grid.
- E-REDES (Q111843687), high voltage (60kV) sub-transmission grid, medium voltage (10-30kV) distribution grid, and the majority of low voltage (400V triphasic, 230V monophasic) distribution grid.
In the Azores and Madeira, there is no true very-high voltage transmission grid, owed to the small size of the archipelagos that doesn't require long-distance electricity transmission.
In the Azores, the high voltage (30-60kV) transmission grid, the medium voltage (10-30kV, with a small part at 6kV) distribution grid, and the low voltage (400V) distribution grid, are operated by EDA - Eletricidade dos Açores (Q131463417). Every island has an isolated power grid system, so EDA assigns different roles (transmission vs. distribution) to the same voltage levels depending on the specific needs of each island[1].
In Madeira, the high voltage (30-60kV) transmission, the medium voltage (6.6kV) distribution grid, and the low voltage (400V) distribution grid, are operated by EEM - Empresa de Eletricidade da Madeira[2]. (Q138337537). The two islands with electricity (Madeira and Porto Santo) have isolated power grids. In Madeira, the 30kV voltage level is mostly used in transmission, although 2.6% of medium/low voltage substations are fed at 30kV[2].
| Operator | Network | Website | Wikipedia | Operating area | Label | Taginfo |
|---|---|---|---|---|---|---|
| REN | Transmission | https://www.ren.pt/ | Redes Energéticas Nacionais on Wikipedia | Continental Portugal | operator=REN
|
|
| E-REDES | Subtransmission
Distribution |
https://www.e-redes.pt/ | EDP on Wikipedia | Continental Portugal | operator=E-REDES
|
|
| EDA | Transmission
Distribution |
https://www.eda.pt/ | Azores | operator=EDA
|
| |
| EEM | Transmission
Distribution |
https://www.eem.pt/ | Madeira | operator=EEM
|
|
Some parts of the low voltage distribution grid and medium/low voltage substations are managed by smaller operators[3], most of which are cooperative companies (co-owned by retail customers), or public companies owned by smaller administrative divisions. These operators typically operate within a single municipality (município) or civil parish (freguesia).
- A Celer - Cooperativa Eletrificação de Rebordosa, C.R.L.
- A Eléctrica de Moreira de Cónegos, C.R.L.
- Casa do Povo de Valongo do Vouga
- CEL - Cooperativa Eléctrica do Loureiro, C.R.L.
- CEVE - Cooperativa Eléctrica de Vale D’Este, C.R.L.
- Cooperativa Eléctrica de Vilarinho, C.R.L.
- CESSN - Cooperativa Eléctrica S. Simão de Novais, C.R.L.
- Cooperativa de Eletrificação A Lord, C.R.L.
- Cooproriz - Cooperativa de Abastecimento de Energia Eléctrica, C.R.
- Junta de Freguesia de Cortes do Meio
Laws on data
Operators of transmission and distribution networks in the high-voltage (45-110kV) and medium-voltage (1-45kV) ranges in Continental Portugal, Azores and Madeira are legally obligated[4] to make available to market agents and other interested parties technical information that allows them to know the networks' characteristics. This information must include:
- Geographical location of power lines and substations, and the geographical area served by the substations;
- The main characteristics of the network, of power lines and substations, as well as their variations according to the season of the year;
- For substations' medium, high and very-high voltage busbars, their triphasic symmetric short circuit, maximum and minimum powers;
- The type of grounding;
- Maximum and minimum power transit values in lines, and substations' loading powers;
- Information on available capacity of networks;
- Identification and reason for the main restrictions of networks' capacities;
- Quantitative and qualitative information regarding service continuity and voltage waveform quality.
Moreover, this information must be publicly accessible via the Internet, and published yearly.
This information must be provided yearly by network operators to ERSE (Entidade Reguladora dos Serviços Energéticos - Regulatory Body for Energy Services) by March 15th of each year, reporting to the status of the network on December 31st of the previous year. So most network operators also publish their network characteristics reports in their websites on March 15th, although there is not a fixed limit on when network operators may make those documents publicly available; particularly, E-REDES tends to delay their reports' publishing, sometimes up to 6 months.
Here is a list of the companies that must publish their yearly network characteristics reports, since they are legally recognized as the only operators of medium, high and very-high voltage power grids, as well as the corresponding URLs where their reports are customarily published:
- REN (transmission): https://mercado.ren.pt/PT/Electr/AcessoRedes/AcessoRNT/CaractRNT
- E-REDES (subtransmission & distribution): https://www.e-redes.pt/pt-pt/sobre-nos-e-redes/organizacao/documentacao-relevante
- EDA (Azores): https://www.eda.pt/regulacao/regulamentos/regulamento-de-acesso-as-redes-e-as-interligacoes
- EEM (Madeira): https://www.eem.pt/pt/conteudo/publicacoes/caracterizacao-da-rede/
This means that power grid information in Portugal is relatively high quality, readily accessible and up-to-date. E-REDES goes even further than just publishing reports in PDF format, and has its own Open Data Portal where it publishes information about its power networks in API and geo-referenced dataset formats (although some datasets are not frequently updated). See more in Power Networks/Portugal#Data sources
State of the map
Network

As of 2026-04-23, the state of the mapped power grid in Portugal is as follows:
| Voltage | Expected | Mapped | |||
|---|---|---|---|---|---|
| Lines | Transmission network | 400 kV | 3,465.2 km[5] | 3,508.4 km[6] (100%) | |
| 220 kV | 3,916.1 km[5] | 3,952.6 km[7] (100%) | |||
| 150 kV | 2,513.9 km[5] | 2,739.4 km[8] (100%) | |||
| 130 kV | 38.2 km[9] | 38.1 km[10] (100%) | |||
| Subtransmission network | 60 kV | 9,742 km[11] | 9,604 km[12] (99%) | ||
| Distribution network | Regional | 6–30 kV (aerial) | 60,015 km[11] | 51,097 km[13] (85%) | |
| 6–30 kV (underground) | 15,838 km[11] | 364 km[14] (0.7%) | |||
| Local | 400 V (aerial) | 116,859 km[15] | 22.5 km[16] (0.02%) | ||
| 400 V (underground) | 35,259 km[15] | 0 km[17] (0%) | |||
| Substations | Regional Distribution | High-to-Medium | 437[9][11] | 433[18] (99%) | |
| Local Distribution | Medium-to-Low | 72,427[15][19] | 6,249[20] (9%) | ||
- Very-high voltage power lines (operated by REN) are all mapped, and are updated as needed based on users' information about new line construction, and cross-checked every year against the operator-published Electric Network Description report.
- High voltage power lines (E-REDES, 60kV) are all mapped within the limits of what's possible and reasonable, based on users' information about new line construction, and cross-checked every year against the operator-published network characteristics report. The reports published by E-REDES have a lower standard of quality than those published by REN, so some of the lines listed in their reports are no longer operating.
- Medium voltage power lines (E-REDES, 10-30kV) aerial mapping coverage varies a lot by region, here is a summary of mapping coverage estimates per district:
- Faro: 100%
- Beja: 100%
- Évora: 100%
- Portalegre: 100%
- Castelo Branco: 100%
- Guarda: 100%
- Lisboa: 100%
- Santarém: 100%
- Leiria: 100%
- Coimbra: 100%
- Viana do Castelo: 90%
- Braga: 75%
- Aveiro: 66%
- Porto: 66%
- Vila Real: 40%
- Viseu: 40%
- Bragança: 33%
Even districts with 100% mapping are liable to have some minor power lines not mapped yet.
Electricity generation

The total installed power generation capacity in Portugal is 22.7 GW as of 2026-02-25 (calculated by removing sub-windfarms and only counting the parent windfarms once). The primary energy sources in Portugal are (with percentages corresponding to power production rating, not actual production)[21]:
- Hydroelectric: 32.6%
- Wind: 26.2%
- Solar: 21.7%
- Gas: 16.5%
- Other: 3%
Hydro and wind power production is concentrated in northern and central Portugal, given the greater altitudes, elevation differences and annual rainfall, whereas solar power production is most common in southern Portugal due to flatter terrain and greater sun exposure.
Project highlights
International Douro Hydropower Cascade
The International Douro, also known as Saltos do Douro (lit. Douro Jumps) is the 122 km part of the Douro river that runs along the Portugal-Spain border, between Salto de Castro
Salto de Castro and Barca d'Alva
Barca d'Alva, and it is a region where the Douro river eroded deep rocky valleys, funneling significant rainfall through an area providing good dam anchoring and large heads (total fall height of 429.5 m), with very high hydroelectric potential. The dams were built between 1946 and 1964, after an agreement between Spain and Portugal in 1927 to split the hydroelectric potential of this stretch. Because of the deep valleys, these dams do not have much storage capacity, but they provide a large amount of hydropower (installed capacity 3.2 GW), particularly during floods when the hydroelectric power plants run almost all incoming water flow through turbines. On the Portuguese side, all of the dams and power plants of the International Douro Hydropower Cascade are owned and operated by Movhera. The system is composed of the following elements, from upstream to downstream:
- Castro Dam (53085066
53085066):
- Castro I (1435158540
1435158540): 84 MW. - Castro II (19674822
19674822): 112.9 MW.
- Castro I (1435158540
- Miranda Dam (71588050
71588050):
- Miranda I (19549760
19549760): 180 MW. - Miranda II (1226928891
1226928891): 189 MW.
- Miranda I (19549760
- Picote Dam (2520396
2520396):
- Bemposta Dam (533091902
533091902):
- Aldeadávila Dam (215669321
215669321):
- Aldeadávila (8554482717
8554482717): 1,242.9 MW.
- Aldeadávila (8554482717
- Saucelle Dam (207255601
207255601):
Cávado-Rabagão-Homem Hydroelectric System
The Cávado-Rabagão-Homem Hydroelectric System is a hydroelectric system operated by EDP in the Cávado River
Cávado River basin, including its major tributaries, the Rabagão River on the left and the Homem River
Homem River on the right. It was kickstarted by the 1945 concession of construction rights to Hidroeléctrica do Cávado (Cávado Hydroelectric), and this first stage lasted between 1946-1964, with the Venda Nova (1951), Salamonde (1953), Caniçada (1955), Paradela (1958) and Upper Rabagão & Cávado Dams (1964); later Hidroeléctrica do Cávado was merged into the Companhia Portuguesa de Eletricidade (Portuguese Electricity Company) in 1969, and the last dam of the system was built, Vilarinho das Furnas (1972). The final stage in 2005-2017, now under EDP, consisted of power production increases through new power plants Frades I (2005) & II (2017) and Salamonde II (2016), served by the existing dams.
The system is composed of the following elements:
- Upper Rabagão (2449098
2449098): Rabagão.
- Upper Rabagão Hydroelectric Power Plant 18745193
18745193 (1964): 66 MW reversible, 973 GWh storage.
- Upper Rabagão Hydroelectric Power Plant 18745193
- Venda Nova Dam (18456918
18456918): Rabagão, 125 GWh storage.
- Venda Nova Hydroelectric Power Plant 1427805693
1427805693 (1951): 88 MW, discharges to Salamonde Dam. - Frades I Hydroelectric Power Plant 455366572
455366572 (2005): 191.4 MW reversible, discharges to Salamonde Dam. - Frades II Hydroelectric Power Plant 455366583
455366583 (2017): 736 MW reversible, discharges to Salamonde Dam.
- Venda Nova Hydroelectric Power Plant 1427805693
- Vilarinho das Furnas Dam (16375240
16375240): Homem, discharges to Homem that meets with Cávado in Amares, a long distance after Caniçada.
- Vilarinho das Furnas Hydroelectric Power Plant 805803314
805803314 (1972): 125 MW reversible, discharges to Caniçada Dam.
- Vilarinho das Furnas Hydroelectric Power Plant 805803314
- Upper Cávado Dam (18456918
18456918): Cávado, does not have hydropower capabilities but has an interbasin transfer conduit to Upper Rabagão Dam. - Paradela Dam (15342602
15342602): Cávado.
- Paradela Hydroelectric Power Plant 1427805692
1427805692 (1956): 56 MW, discharges to Salamonde Dam. It is housed in the same building as Venda Nova Hydroelectric Power Plant.
- Paradela Hydroelectric Power Plant 1427805692
- Salamonde Dam (18913985
18913985): Cávado, receives waterflow from Rabagão.
- Salamonde I Hydroelectric Power Plant 1426280013
1426280013 (1953): 41 MW, discharges to Caniçada Dam. - Salamonde II Hydroelectric Power Plant 1426280012
1426280012 (2016): 222.7 MW reversible, discharges to Caniçada Dam.
- Salamonde I Hydroelectric Power Plant 1426280013
- Caniçada Dam (2441815
2441815): Cávado, receives waterflow from Homem.
- Caniçada Hydroelectric Power Plant 1227767799
1227767799 (1954): 62 MW.
- Caniçada Hydroelectric Power Plant 1227767799
Tâmega Gigabattery
The Tâmega Gigabattery, also known as the Tâmega Hydroelectric Complex, is a large-scale project by Iberdrola to develop an integrated hydroelectric system that provides massive storage and pumping capabilities, with a total installed power production capacity of 1.43 GW[22] and a storage capacity of 42 GWh[23]. It was started in 2018 and the hydroelectric component was finished in 2024. The goal is to make an efficient use of hydroelectric potential of the upper Tâmega River
Tâmega River, but most importantly to equip the Portuguese power grid with a massive pumped-storage system. It is composed of a cascade of dams and hydroelectric power plants with large heads and powerful reversible turbines, to store power when it is cheapest by pulling power from the grid to pump rainwater upstream, and produce power when it is most expensive using the same pumped rainwater. This concept has been expanded more recently to include hybridization with wind power, with the construction of the Tâmega Windfarm
Tâmega Windfarm. It is composed of the following elements:
- Alto Tâmega Hydroelectric Power Plant (1429372113
1429372113): 160 MW production, 20 GWh storage. Its main role is water flow regulation of the Tâmega River
Tâmega River for the rest of the system, so it does not have pumping capabilities. - Daivões Hydroelectric Power Plant (767834338
767834338): 118 MW production. Its dam in the Tâmega River
Tâmega River impounds the lower reservoir of the pumped-storage system, the Daivões Reservoir
Daivões Reservoir. - Gouvães Hydroelectric Power Plant (768250326
768250326): 880 MW pumped-storage, 20 GWh storage. Its dam in the Torno River
Torno River impounds the upper reservoir of the system, the Gouvães Reservoir
Gouvães Reservoir. It is a massive underground hydropower plant, that also includes a 7.4 km underground pressurized water circuit connecting the upper and lower reservoirs to the plant. - Tâmega Windfarm (19953863
19953863): 274 MW production.
Operators
Here is a list of the largest power producers in Portugal.
| Operator | Total generation capacity (share %) | Largest plants | Note |
|---|---|---|---|
| EDP - Energias de Portugal | 7,237.9 MW (31.8%) | Ribatejo Termoelectric Lares Combined Cycle Frades II Hydroelectric |
A leftover of the nationalization period, EDP still owns and operates most hydroelectric and termoelectric power plants. |
| Movhera | 1,699.0 MW (7.5%) | Picote II Hydroelectric Bemposta I Hydroelectric Bemposta II Hydroelectric |
A consortium partly owned by Engie. It owns six major dams in the upper Douro, and their corresponding power plants. |
| Iberdrola | 1,605.0 MW (7.1%) | Gouvães Hydroelectric Tâmega Windfarm Alto Tâmega Hydroelectric Daivões Hydroelectric |
Spanish electrical utilities company. In Portugal, Iberdrola is mostly investing in its Tâmega Gigabattery project, a hydropower cascade with massive storage and pumping capabilities. |
| EDP Renováveis | 1,397.4 MW (6.2%) | Alto da Coutada Windfarm Beiras Windfarm Sincelo Windfarm |
Renewables branch of EDP, mostly owns windfarms. |
| Finerge | 1,379.2 MW (6.1%) | Alto Minho I Windfarm Alto Douro Windfarm Douro Sul Windfarm |
Mostly owns windfarms. |
| Energy Means Life | 1225.4 MW (5.4%) | Tapada do Outeiro Combined Cycle Terra Fria Windfarm Mértola Windfarm |
Portuguese company operating Tapada do Outeiro Combined Cycle Power Plant. Owned by Marubeni group. Results from the split of the joint venture TrustEnergy between Engie and Marubeni. |
| Engie | 1,090.1 MW (4.8%) | Pego Termoelectric Terras Altas de Fafe Windfarm Prados Windfarm |
French electricity utilities company, owns the Pego Termoelectric Power Plant. |
| Ventient Energy | 902.7 MW (4.0%) | Serra dos Candeeiros Windfarm Pampilhosa da Serra Windfarm Chão Falcão Windfarm |
Mostly owns windfarms. |
| GreenVolt | 705.0 MW (3.1%) | Nisa Photovoltaic Tábua Photovoltaic Celbi Mondego Biomass |
Originally a subsidiary of EDP, it was acquired by the wood pulp conglomerate Altri in 2018. It was formally rebranded as GreenVolt in March 2021 to manage the biomass power plants operated by the conglomerate, but with a goal set on investing in other renewable power sources, after poaching former senior manager of EDP and CEO of EDP Renováveis, João Manso Neto. |
| TotalEnergies Renewables Portugal
(old Generg) |
561.2 MW (2.5%) | Pinhal Interior Windfarm Gardunha Windfarm Caramulo Windfarm |
Previously Generg, mostly owns windfarms. It is owned by french Big Oil Total. |
Network description
Voltages and frequency
Frequency : 50 Hz
| Network | Voltage | Comments | Appearance |
|---|---|---|---|
| Transmission | 400 kV | Very high voltage power lines, part of the National Transport Network. Operated by REN. | REN identifies its power lines by power line sections, not by circuits, so each line and branch is individually listed; hence why all 150-400kV power=circuit relations always have power=line_section relations as members with role section, and never have power=line or similar as members with role section, so that power=line_sections may be listed in a similar format that REN uses in its annual network characteristics report.
|
| 220 kV | |||
| 150 kV | |||
| 130 kV | Legacy voltage used in power lines that start in Lindoso Hydro |
The only two lines using this voltage are Lindoso - Conchas (interconnection with Spain), which has been disassembled in 2025 on the Portuguese side, and Lindoso - Pedralva, with the Pedralva substation having a unique 130/150kV transformer to transform power into 150kV, which is one of the standard very high voltages used in Portugal. | |
| Distribution | 60 kV | High voltage power lines, part of the National Distribution Network. Operated by E-REDES. | These power lines do not serve customers directly; they may sometimes serve large-scale customers that need to draw or inject large amounts of power into the network.
Aside from that, they're mostly used by E-REDES to balance loads between its high/medium voltage substations without using REN's very high voltage network, and power lines are point-to-point, so it can be described as a subtransmission network. Aerial: power lines, in groups of 3 cables, with very rare branching. It is fairly common for high voltage power lines to have 1 or 2 circuits. E-REDES identifies its power lines by power line sections, not by circuits, so each line and branch is individually listed; hence why all 60kV Distribution substations (high/medium voltage):
|
| 30 kV | Medium voltage power lines, part of the National Distribution Network. Operated by E-REDES.
These power lines connect directly to small industries, or to minor substations. |
Aerial: power lines, in groups of 3 cables, with often branching. Most medium voltage power lines only have one circuit, but occasionally power poles may support two circuits, one on each side of the pole.
Power poles: may either be concrete poles with the shape of an H when seen vertically, or steel lattice poles. It is common for medium voltage power lines to transition from aerial to underground. Many of these poles are numbered sequentially with numbers painted at eye-level, typically up to 200 at most, and very rarely may also have the name of the medium voltage power line that the pole supports. Some poles have mechanical power switches, usually identified by a steel rod/mechanism running through the vertical extent of the pole, and a black rectangle painted in the pole at about eye-level with white letters; most switches are manually activated (usually start with "SEC" if they're a disconnector - seccionador and can only isolate non-energized circuits, or "INT SEC" if they're an load-break switch - interruptor/seccionador and can interrupt an energized circuit with nominal current values). Some switches may be remotely activated (always start with "OCR" because it's a remote switch - órgão de corte de rede), for these switches you can see a large white box containing the switching equipment on top of the pole, and sometimes see a radio antenna attached to the side of the pole. H-profile concrete power pole supporting a medium/low voltage transformer, with a power switch.
H-profile concrete power pole supporting a medium voltage power line, with branch that transitions underground without a switch.
H-profile concrete power pole supporting a medium voltage power line, with transition to underground and a switch.
Detail near the base of a pole, with pole referenced number painted in white over black background.
In the power line: Distribution substations (high/medium voltage): most medium voltage power lines connect to distribution substations through poles with transition to underground. Most medium voltage power lines inside distribution substations are underground. In most distribution substations, medium-voltage switching equipment, busbars and auxiliary medium/low voltage transformers are located indoors. Some older substations may have the medium voltage power lines connected to portals, but these power lines typically transition to underground after connecting to the portal. power=pole material=concrete structure=solid line_attachment=anchor transformer=distribution switch=mechanical
| |
| 15 kV | |||
| 10 kV | |||
| 6 kV | Legacy medium voltage power lines. Operated by E-REDES, they are part of the National Distribution Network. | Only exists in the cities of Portalegre and Castelo Branco[24]. Efforts are being undertaken to convert these power lines into 30 kV, to match the voltages used by E-REDES in more recent lines set up in low-population areas around these two cities[25].
90% of the 6kV distribution network is underground[24], since this voltage level is only used in the urban areas of the cities of Portalegre and Castelo Branco. | |
| 400 V | Low voltage power lines/cables, part of the National Distribution Network. Operated for the most part by E-REDES. | Aside from E-REDES, there are 10 other, municipality-level low voltage network operators as listed by ERSE[26], most of which are cooperative/municipal companies that historically predate E-REDES and its old equivalent EDP.
Aerial: typically copper cables insulated with plastic, supported by wooden poles with anchor attachments or street lights. Very rarely, and only in rural areas, they may appear as non-insulated power lines in groups of 3, vertically aligned, supported by wooden poles with pin attachments. Underground: most of the low-voltage power grid is made of underground cables in towns and cities. Distribution: made mostly through street cabinets, that do not house transformers. |
These values are used for quality control in some OSM tools. If you change them, please also report it by creating an issue on GitHub. More information about country voltage QA.
There are other frequently used voltages, such as:
- 25kV, in most of the train traction system.
- 1.5kV DC, in the train traction system of the Cascais railway line.
- 30kV, very common in internal power lines/cables of wind farms in Continental Portugal.
- It is very common for power generators to generate power at non-standard voltages, usually in the range of 1-20kV, which are then stepped up by step-up/generator transformers before connecting to the distribution or transmission networks.
Interconnections
| Neighbour country | Structure name | Technology | Voltage | Local end | Foreign end | OSM circuit | Notes |
|---|---|---|---|---|---|---|---|
| Spain | Alto Lindoso - Cartelle | 50Hz AC | 400kV | Alto Lindoso |
Cartelle |
Alto Lindoso - Cartelle 1 Alto Lindoso - Cartelle 2 |
Double circuit interconnection. |
| Spain | Lagoaça - Alveadávila | 50Hz AC | 400kV | Lagoaça |
Aldeadávila II |
Lagoaça - Aldeadávila |
|
| Spain | Falagueira - Cedillo | 50Hz AC | 400kV | Falagueira |
Cedillo |
Falagueira - Cedillo |
|
| Spain | Alqueva - Brovales | 50Hz AC | 400kV | Alqueva |
Brovales |
Alqueva - Brovales |
|
| Spain | Tavira - Puebla de Guzmán | 50Hz AC | 400kV | Tavira |
Puebla de Guzmán |
Tavira - Puebla de Guzmán |
|
| Spain | Pocinho - Aldeadávila | 50Hz AC | 220 kV | Pocinho |
Aldeadávila II |
Pocinho - Aldeadávila 1 Pocinho - Aldeadávila 2 |
Double circuit interconnection. |
| Spain | Pocinho - Saucelle | 50Hz AC | 220 kV | Pocinho |
Saucelle II |
Pocinho - Saucelle |
|
| Spain | Alcáçova - Riocaya | 50Hz AC | 60kV | Alcáçova |
Riocaya |
Alcáçova - Riocaya |
On the Portuguese side, this interconnection is operated at the nominal voltage of 60kV, but on the Spanish side it sometimes appears with the nominal voltage of 66kV[27]. It was decided to tag the circuit as 60kV, as the Portuguese side always uses 60kV nominal voltage, and in the case of Spain most documents mention 66kV but some also mention 60kV (example: [28]). |
Planned projects
- ...
Data sources
| Publisher | Source | License | Date | Suitable for OSM | Notes |
|---|---|---|---|---|---|
| REN | National Transmission Grid characteristics for the purpose of network access - situation on 31 December 2024 | (c) REN | 31 December 2024 | No | PDF file. Contains a map of the transmission network in raster format (and the power lines' paths are simplified, so they only roughly follow their real paths). Identifies all the very-high voltage (150-400kV) power lines, including their length, type (number and type of conductors) and technical specs. Also identifies all very-high voltage (150-400kV) substations, including their condenser capacity. Also identifies all transformers in very-high voltage substations, including their reference number, type (regular transformer vs. auto-transformer, triphasic vs three monophasic devices, etc.), voltage levels, rating (in MVA) and start date. |
| E-REDES | Available Hosting Capacity in the National Distribution Grid | CC BY 4.0 | Estimated 2023 | Yes | Power distribution network (10-30kV) in Continental Portugal. You can query the MT power lines served by each HV/MV substation, and get it in GeoJSON format. This dataset is only suitable to locate power lines outside substations; it also does not provide information on power switches nor minor distribution substations. |
| E-REDES | Secondary Substations | CC BY 4.0 | 31 Dec 2022 | Yes | List of georeferenced minor distribution substations (10-30kV to 400V) in Continental Portugal, with the minor substations' reference number. For each minor distribution substation, it identifies the type (pole with transformer, transformer tower, service building, etc.) and the total rating in kVA. You can query the API or export the dataset as CSV/JSON. |
| E-REDES | Distribution networks characteristics on 31 December 2024 | (c) E-REDES | 31 December 2024 | No | PDF file. In addition to the datasets above by E-REDES, it contains a map with subtransmission power lines (60kV) in vector format that can be converted to .osm format, and a list of all subtransmission power line sections (60kV), including their length, type (number and type of conductors) and technical specs. |
| E-REDES | Low-voltage distribution networks characteristics on 31 December 2024 | (c) E-REDES | 31 December 2024 | No | PDF file. As a complement to the Secondary Substations dataset, it also mentions the number of transformers in each minor substation. |
| E-REDES | Low voltage poles | CC BY 4.0 | 23 August 2023 | Yes | List of georeferenced power poles supporting low-voltage power cables/lines, that have been deemed suitable to also support telecommunications cables. This is meant as a way for E-REDES to tell telecom operators which power poles they may use to support telecom cables, so this is not an extensive list of low voltage power poles. |
Electricity generation
Mapping process and community
Data
The following datasets are provided under a Creative Commons Attribution 4.0 International (CC BY 4.0) open license. You are allowed to use and include them in OSM as long as you add the following tags to each derived element:
operator=*- Usually it's the name of the dataset provider (e.g., REN, E-REDES).operator:wikidata=*- Wikidata number for the operator.source=*- Name of the dataset.source:date=*- Date of publication.
Dataset abbreviations:
- AT - High and very high voltage network (60–400 kV).
- MT - Medium voltage network (6–30 kV).
- BT - Low voltage network (400 V).
| Dataset | Name | Provider | Date | Format | Description |
|---|---|---|---|---|---|
| AT | RNT Characterization in 2024[29][30] | REN | 2025-03-31 | The full name of the PDF document is Characterization of the National Transmission Network (RNT) for purposes of Network Access and provides with technical information on the characteristics of the networks. These include...
Tags to use: | |
| Technical Data for 2024[31][32] | REN | 2025-04-14 | Provides electricity and gas information. These include...
Tags to use: | ||
| MT | Characterization of the Distribution Network in 2022[33][34] | E-REDES | 2023-03-31 | Caracterização das redes de distribuição (2022). In Anexo 2 you can find the location and voltage of the AT e MT lines, of the AT/MT e MT/MT substations operated by E-REDES. In Anexo 3 there is a list of substations and postos de corte operated by E-REDES. In Anexo 4 there is a list of AT lines operated by E-REDES, with references, name, type of conducting cable and lengths. In Anexo 6 there is a list of substation, including the municipality it belongs to.
Tags to use: | |
| Network Features in 2024[35] | E-REDES | 2025-10-30 | CSV, JSON, Excel, Parquet | Características da rede. Main characteristics of the distribution substation network, including their name, location, transformation ratio, installed power, short-circuit powers and other relevant parameters for equipment sizing. An online slippymap is available here.
Tags to use: | |
| Reception Capacity in the National Distribution Network in 2024 [36] | E-REDES | 2025-12-27 | CSV, JSON, Excel, Parquet | Capacidade de receção na Rede Nacional de Distribuição. Information and geographic location (not georeferenced) of the AT/MT substations operated by E-REDES, with area of influence of MT lines for each. An online slippymap is available here. Shows the estimated capacity for receiving generation power for the high and medium voltage busbars.
Tags to use: | |
| Secondary Substations in 2026[37] | E-REDES | 2026-03-06 | CSV, JSON, Excel, GeoJSON, Shapefile, KML, FlatGeobuf, GPX, Parquet | Postos de transformação distribuição. Geographic location (georeferenced) of MT/BT minor distribution substations, with information on installed power and utilization percentage. An online slippymap is available here.
Tags to use: | |
| BT | Low Voltage Poles in 2023[38] | E-REDES | 2023-08-23 | CSV, JSON, Excel, GeoJSON, Shapefile, KML, FlatGeobuf, GPX, Parquet | Apoios de baixa tensão . Geographic location (georeferenced) of the poles supporting the overhead BT cable network. An online slippymap is available here.
Tags to use: |
Towers and Poles
| Picture | Value | Description | Occurrence | Comments |
|---|---|---|---|---|
design=delta
|
Two insulators on two sides of the pole, and one insulator on the top of the pole. | 46.8% | ||
design=one-level
|
Single cross-arm, usually supporting only one circuit. | 25.0% | ||
design=three-level
|
Three cross-arms, usually supporting one to three circuits. | 12.4% | ||
design=triangle
|
Two insulators are mounted on the uppermost and lowermost cross-arms and at the pole's front side, and one insulator is mounted on the middle cross-arm and at the back side of a pole. | 10.7% | ||
design=barrel
|
Similar to design=three-level, but the middle level cross-arms are longer than the upper and lower cross-arms, giving the conductor arrangement a barrel-like shape.
|
4.3% | ||
design=armless_triangle
|
Similar to design=triangle, but with insulators mounted on the pole instead on the cross-arm. Two insulators are placed on one side of the pole, and one insulator is placed on the other side
|
0.3% | ||
design=two_level
|
Two cross-arms, usually supporting two circuits. | 0.3% |
Mapping success stories
TODO : Success stories are designed to highlight important contributions. Have you significantly improved the cartography of a country (added a new line, a power station, etc.)? Don't be shy, let us know below.
- Example : NAME [DATE YYYY-MM-DD]: My success stories in words.
Encountered problems and places to improve
- ....
Use of mapping strategies
TODO : Mapping strategies refer to Power networks/Guidelines#Mapping strategies. They are used for a methodical improvement of the OSM database. Once you have fully applied a strategy in this country, you should add or update your name, the date, the strategy, and a comment below. This way, other users can see whether it is worthwhile to carry out further investigations.
- Example : Search for "Unfinished major power lines" - last time applied by XXX [2025-MM-DD]
- .... - last time applied by XXX [2025-MM-DD]
References
- ↑ https://files.eda.pt/edasharepointfiles/Biblioteca%20Internet%20EDA/Regula%C3%A7%C3%A3o/Regulamentos/Regulamento%20de%20Acesso%20%C3%A0s%20Redes%20e%20Interliga%C3%A7%C3%B5es/Componentes/CARE%202023.pdf
- ↑ 2.0 2.1 https://www.erse.pt/media/cuskjng5/pdirtd-ram-2022-2024.pdf
- ↑ https://www.erse.pt/eletricidade/funcionamento/distribuicao/
- ↑ ERSE (2023, 27 de julho). Regulamento do Acesso às Redes e às Interligações do Setor Elétrico (RARI) [Regulamento nº 818/2023]. https://www.erse.pt/media/1s3htdaa/rari_reg818_2023.pdf
- ↑ 5.0 5.1 5.2 https://mercado.ren.pt/PT/Electr/AcessoRedes/AcessoRNT/CaractRNT/BibRelAno/Caracteriza%C3%A7%C3%A3o%20da%20RNT%2031-12-2025.pdf
- ↑ area["ISO3166-1"="PT"][admin_level=2]->.boundaryarea; ( way(area.boundaryarea)[power=line][!line][disused!=yes][operator="REN"][voltage~400000]; way(area.boundaryarea)[power=cable][!line][disused!=yes][operator="REN"][voltage~400000]; ); (._;>;); out meta;
- ↑ area["ISO3166-1"="PT"][admin_level=2]->.boundaryarea; ( way(area.boundaryarea)[power=line][!line][disused!=yes][operator="REN"][voltage~220000]; way(area.boundaryarea)[power=cable][!line][disused!=yes][operator="REN"][voltage~220000]; ); (._;>;); out meta;
- ↑ area["ISO3166-1"="PT"][admin_level=2]->.boundaryarea; ( way(area.boundaryarea)[power=line][!line][disused!=yes][operator="REN"][voltage~150000]; way(area.boundaryarea)[power=cable][!line][disused!=yes][operator="REN"][voltage~150000]; ); (._;>;); out meta;
- ↑ 9.0 9.1 Características da Rede (2024) - E-REDES
- ↑ https://overpass-turbo.eu/s/2kP2
- ↑ 11.0 11.1 11.2 11.3 https://www.e-redes.pt/sites/eredes/files/2026-04/E-REDES_Artigo18_RARI2025_Caracterizacao_Redes_Distribuicao_MT_AT_a_31.dez_.2025.pdf
- ↑ area["ISO3166-1"="PT"][admin_level=2]->.boundaryarea; ( way(area.boundaryarea)[power={power}][!line][disused!=yes][operator="E-REDES"][voltage~60000]; way(area.boundaryarea)[power=cable][!line][disused!=yes][operator="E-REDES"][voltage~60000]; ); (._;>;); out meta;
- ↑ https://overpass-turbo.eu/s/2kPn
- ↑ https://overpass-turbo.eu/s/2kPo
- ↑ 15.0 15.1 15.2 Relatório da Qualidade de Serviço (2025) - E-REDES
- ↑ https://overpass-turbo.eu/s/2kRX]
- ↑ https://overpass-turbo.eu/s/2kRZ]
- ↑ Overpass (substation=distribution in Portugal)
- ↑ Postos de Transformação Distribuição (PTD) (2024) - E-REDES
- ↑ Overpass (substation=minor_distribution in Portugal in Portugal)
- ↑ OpenInfraMap, collected on 2026-02-24. https://openinframap.org/stats/area/Portugal
- ↑ Sourced from OpenStreetMap on 2026-02-26.
- ↑ https://www.iberdrola.com/quem-somos/nossa-atividade/energia-hidreletrica/gigabateria-tamega
- ↑ 24.0 24.1 https://repositorio-aberto.up.pt/bitstream/10216/68165/1/000154871.pdf
- ↑ https://www.cm-portalegre.pt/wp-content/uploads/2022/09/ata_03_2013_cmp.pdf
- ↑ https://www.erse.pt/eletricidade/funcionamento/distribuicao/
- ↑ https://www.sistemaelectrico-ree.es/en/2021/spanish-electricity-system/transmision/electricity-transmission-grid-facilities
- ↑ https://www.ree.es/sites/default/files/01_ACTIVIDADES/Documentos/Mapas-de-red/mapa_transporte_iberico_2018.pdf
- ↑ https://mercado.ren.pt/EN/Electr/NetworkAccess/RNTAccess/RNTSpec/Pages/default.aspx
- ↑ https://mercado.ren.pt/PT/Electr/AcessoRedes/AcessoRNT/CaractRNT/BibRelAno/Caracteriza%C3%A7%C3%A3o%20da%20RNT%2031-12-2024.pdf
- ↑ https://datahub.ren.pt/en/publications/
- ↑ https://www.ren.pt/media/al3n1imk/ren-dados-tecnicos-2024.pdf
- ↑ https://www.e-redes.pt/en/node/30996
- ↑ https://www.e-redes.pt/sites/eredes/files/2023-04/E-REDES_Caracterizacao_das_Redes_de_Distribuicao_a_31.dez_.2022_.pdf
- ↑ https://e-redes.opendatasoft.com/explore/dataset/caracteristicas-da-rede/table/
- ↑ https://e-redes.opendatasoft.com/explore/dataset/capacidade-rececao-rnd/table/
- ↑ https://e-redes.opendatasoft.com/explore/dataset/postos-transformacao-distribuicao/table/
- ↑ https://e-redes.opendatasoft.com/explore/dataset/postos-transformacao-distribuicao/table/


